On 22 December 2023, Transgrid submitted its stage 1 contingent project application to us seeking an increase to its revenue to fund the early works stage of the Victoria to NSW Interconnector West (VNI West) contingent project in accordance with clause 6A.8.2 of the NER. This VNI West contingent project application relates to the NSW portion that Transgrid is responsible for, which forms part of the overall construction of a new 500 kV transmission line between Victoria and NSW.
We invited stakeholders to make submissions on Transgrid's contingent project application. Submissions closed on 1 March 2024.
On 6 May 2024, we published our decision in relation to Transgrid's Victoria to NSW Interconnector West (VNI West) contingent project application.
On 23 September 2026, VicGrid and Transgrid, the joint proponents of VNI West, notified us that they consider there has been a material change in circumstances for the project under clause 5.16A of version 202 of the NER. On 18 November 2026, we advised VicGrid and Transgrid that the circumstances requiring the RIT-T to be reapplied under clause 5.16A.4(n) of version 202 of the NER have not been shown to have arisen. We will therefore not make a determination under that clause at this stage.