On 7 June 2024 Jemena submitted a cost pass through application to the AER, seeking to recover costs incurred in response to the Victorian Government introducing the Victorian Emergency Backstop Mechanism (VEBM). 

Jemena is proposing an increase in its revenue allowance of approximately $7.8 million ($2021) in the current regulatory control period.

Jemena - Stage 2 backstop cost pass through application - June 2024

Authors
Jemena
Content type
Document

Attachment A - VEBM Stage 1 - order in council GG2023S542

Authors
Jemena
Content type
Document

Attachment B - VEBM Stage 2 - order in council GG2024S031

Authors
Jemena
Content type
Document

Attachment D - AER - JEN 2021-26 Final Decision SCS PTRM - 2024-25 RoD update - baseline

Authors
Jemena
Content type
Document

Attachment E - AER - JEN 2021-26 Final Decision SCS PTRM - 2024-25 RoD update - update

Authors
Jemena
Content type
Document

Confidentiality claims

Jemena's confidentiality claims can be found in its application document above; see Jemena - Stage 2 backstop cost pass through application - June 2024, Attachment G (pp. 35-38).

Submissions

-

We invited energy consumers and other interested parties to make submissions on Jemena’s VEBM pass through application by close of business 31 July 2024.