Overview

Application

-

On 28 February 2025, TasNetworks submitted a cost pass through application seeking to recover the costs it has incurred as a result of the August-September 2024 storm in Tasmania. TasNetworks is proposing an increased revenue allowance of $4.6 million ($nominal, smoothed) to be recovered over the final three years of the current regulatory period (2024-29) as follows: $1.2 million in 2026-27; $1.9 million in 2027-28; and $1.5 million in 2028–29.

Confidentiality Claims

Submissions

We invited energy consumers and other interested parties to make submissions on TasNetworks’ cost pass through application by 22 April 2025. We received the following submissions.