Draft decision

The AER published its draft decision to update the interim Contracts and Firmness Guidelines (C&F Guidelines) on 10 June 2025. The draft decision includes an updated draft of the C&F Guidelines, a document that tracks the proposed changes to the previous version, and an Explanatory Statement that outlines these changes and our approach to the consultation.

AER - Explanatory Statement - Interim Contracts and Firmness Guidelines draft decision - 10 June 2025

Authors
AER
Content type
Document

AER - Draft instrument - Interim Contracts and Firmness Guidelines draft decision - 10 June 2025

Authors
AER
Content type
Document

Submissions

-

Interested parties were invited to make submissions on this draft document by 8 July 2025.

We received the following submission.

Origin - Submission - Draft Interim Contracts and Firmness Guidelines - 20 August 2025

Authors
Origin Energy
Content type
Document