On 22 January 2026, we made our final decision on Transgrid’s revenue determination for the 2026–31 regulatory control period for the Enabling Central-West Orana REZ Network Infrastructure Project.

In accordance with clause 53(4) of the Electricity Infrastructure Investment Regulation 2021 (EII Regulation), publication of our determination document and accompanying information will occur as soon as reasonably practicable, following notification from the Infrastructure Planner (EnergyCo) that project financial close has been reached. 

On 10 April 2026, we received notification from EnergyCo that financial close for the CWO Enabling Project has been achieved. We have subsequently published the determination document and accompanying attachments on 14 April 2026. Confidential Appendix C – Rate of return averaging periods will not be published to protect confidentiality.

Documents

AER – Final decision – Transgrid – Central-West Orana Enabling REZ non-contestable project 2026–31 – January 2026

Authors
AER
Content type
Document

AER – Final decision – Transgrid – Central-West Orana Enabling REZ non-contestable project 2026–31 – Appendix A – Quarterly service payments – January 2026

Authors
AER
Content type
Document

AER – Final decision – Transgrid – Central-West Orana Enabling REZ non-contestable project 2026–31 – Appendix B – Adjustment mechanisms – January 2026

Authors
AER
Content type
Document

Models

AER – Final decision – Transgrid – Central-West Orana Enabling REZ non-contestable project 2026–31 – PTRM – January 2026

Authors
AER
Content type
Document

AER – Final decision – Transgrid – Central-West Orana Enabling non-contestable project 2026–31 – Capex model – January 2026

Authors
AER
Content type
Document