The AER received a reference service proposal from Australian Gas Networks (Victoria and Albury) (AGN) for the period 1 July 2028 to 30 June 2033. Under the NGL and the NGR, the AER has the function of reviewing and approving the terms of the proposal. Interested stakeholders are encouraged to consider the indicative dates for the key milestones in this review.
| Milestone | Date* |
|---|---|
| AGN reference service proposal due | 1 June 2026 |
| AER publishes AGN reference service final decision | 30 November 2026 |
| AGN submits access arrangement proposal | 1 June 2027 |
| Stakeholder forum on AGN's access arrangement proposal | Optional |
| Stakeholder submissions onAGN's access arrangement proposal close | July-August 2027* |
| AER publishes access arrangement draft decision | November 2027* |
| AGN submits revised access arrangement proposal | January 2028* |
| Stakeholder submissions on AGN's revised proposal and AER's draft decision close | February 2028* |
| AER publishes access arrangement final decision | April 2028* |
* Please note this timeline is subject to change.