Overview

Sector
Electricity
Segment
Distribution
Region
New South Wales
Status
Current
Commencement date
Effective date

On 30 June 2026, Ausgrid submitted a cost pass through application seeking to recover costs it expects to incur as a result of the varied licence conditions due to the NSW Emergency Backstop Mechanism order. 

This order requires Ausgrid to enable remote solar curtailment during Minimum System Load events, update connection and customer processes, support flexible export limits, meet testing and reporting requirements, and integrate with the NSW Consumer Energy Resources Installer Portal.

Ausgrid has identified total incremental costs (capital and operating expenditure) of $45.3 million (real, $2026).

Key Documents

Key Documents

Ausgrid - Emergency Backstop Cost Pass Through Application - Application - 30 June 2026

Content type
Document