Overview

Sector
Electricity
Segment
Transmission
Region
South Australia
Status
Current
Commencement date
Effective date
AER reference
AER25010607

On 18 September 2025, ElectraNet wrote to the Australian Energy Regulator (AER) requesting a determination on its 2024–25 network support pass through application. ElectraNet’s network support pass through application relates to the difference between actual network support payments and the forecast network support payment amount for 2024–25 included in ElectraNet's 2023–28 revenue determination. 

The AER assessed ElectraNet’s application in accordance with clause 6A.7.2(i) of the NER. The approved negative pass through amount is $1.9 million ($Dec 2026).

Key Documents

Key Documents

ElectraNet - Network Support Pass Through Application 2024-25

Content type
Document

AER - Letter to ElectraNet - 2024-25 Network support cost pass through - 12 February 2026

Content type
Document