Overview

Application

On 5 April 2013, ElectraNet submitted an application to the AER seeking a determination, with respect to the proposed South Australia–Victoria (Heywood) Interconnector Upgrade, that the preferred option satisfies the regulatory investment test for transmission (RIT-T). The AER is considering ElectraNet’s application in accordance with the requirements under clause 5.16.6 of the National Electricity Rules.

Prior to receiving ElectraNet's application, the AER received correspondence from several stakeholders about the South Australia–Victoria (Heywood) Interconnector Upgrade RIT-T. To ensure a transparent and timely process, the AER has published this correspondence (with prior approval of the parties) along with the ElectraNet/AEMO response.

*EnerNoc lodged a formal dispute under clause 5.16.5 of the NER with respect to the ElectraNet/AEMO RIT-T. However, the AER could not consider the dispute as it was not lodged within the timeframe prescribed in the NER. The AER has noted the correspondence as part of its 5.16.6 determination process.

ElectraNet - Heywood RIT-T - Request for Rule 5.16.6 determination - 5 April 2013

Authors
ElectraNet
Content type
Document

Macquarie Generation - Letter to AER - Heywood RIT-T - 5 March 2013

Authors
Macquarie Generation
Content type
Document

NGF - Letter to AER - Heywood RIT-T - 22 February 2013

Authors
National Generators Forum (NGF)
Content type
Document

*EnerNOC - Letter to AER - Heywood RIT-T - 26 February 2013

Authors
EnerNOC
Content type
Document

ElectraNet/AEMO - Response to stakeholder correspondence - Heywood RIT-T - 5 April 2013

Authors
ElectraNet
Content type
Document

Consultation - Comments from stakeholders

The AER invited interested parties to comment on ElectraNet's application . The AER received comments from GDF Suez Australian Energy, Major Energy Users and Macquarie Generation.

GDF Suez - Comments on Heywood Interconnector Upgrade RIT-T - 27 May 2013

Authors
GDF Suez Australian Energy
Content type
Document

MEU - Comments on Heywood Interconnector Upgrade RIT-T - 27 May 2013

Authors
Major Energy Users Inc (MEU)
Content type
Document

Macquarie Generation - Comments on Heywood Interconnector Upgrade RIT-T - 31 May 2013

Authors
Macquarie Generation
Content type
Document

Frontier Economics - Market benefits of Heywood Upgrade: A report prepared for Macquarie Generation - May 2013

Authors
Frontier Economics
Content type
Document

Application - Further information from ElectraNet

In accordance with clause 5.16.6(b)(3) of the NER, the AER requested further information from ElectraNet to assist the AER in making its determination.

ElectraNet - Response to AER information request - 21 June 2013

Authors
ElectraNet
Content type
Document

ElectraNet - Response to AER information request - Attachment - 21 June 2013

Authors
ElectraNet
Content type
Document

Consultation - Further comments from stakeholders

The AER invited GDF Seuz Australian Energy, Major Energy Users and Macquarie Generation to comment on ElectraNet's response to the AER's information request.

Major Energy Users - Comments on ElectraNet's response to AER information request - 5 July 2013

Authors
Major Energy Users Inc (MEU)
Content type
Document

Macquarie Generation - Comments on ElectraNet response to AER information request - 8 July 2013

Authors
Macquarie Generation
Content type
Document

Frontier Economics - Frontier's reponse to ElectraNet information release - 5 July 2013 View details

Frontier non-confidential response to ElectraNet-AEMO.docx
DOCX (189.65KB)
Frontier non-confidential response to ElectraNet-AEMO.pdf
PDF (404.55KB)
Authors
Frontier Economics
Content type
Document

Consultation - ElectraNet response to further stakeholder comments

The AER requested ElectraNet provide a response to further stakeholder comments about the congestion hours modelled in the Heywood RIT-T.  

ElectraNet - response to further stakeholder comments - 24 July 2013

Authors
ElectraNet
Content type
Document

Consultation - Heywood Interconnector Upgrade RIT-T modelling workshop

On the 18 July 2013 the AER met with ElectraNet and AEMO to discuss potential issues which stakeholders had raised about the cost-benefit analysis and modelling in the Heywood Interconnector Upgrade RIT-T.

Meeting minute - AER workshop with AEMO and ElectraNet - Heywood Interconnector RIT-T - 18 July 2013 View details

Meeting minute - AER workshop with AEMO and ElectraNet - Heywood Interconnector RIT-T.DOCX
DOCX (62.26KB)
Meeting minute - AER workshop with AEMO and ElectraNet - Heywood Interconnector RIT-T.pdf
PDF (213.78KB)
Authors
AER
Content type
Document