Owner
Queensland Government
Covered by regulation
Yes
Source
State of the Energy Market 2014
Current regulatory period: 1 July 2010 - 30 June 2015
| Customer numbers |
Line length (km) |
Maximum demand 2012-13 (MW) |
Asset base June 2013 ($million) |
| 710 431 |
160 110 |
3 420 |
8 837 |
Decisions
On 27 March 2024 the AER granted a waiver for Ergon Energy to trial battery energy storage unit, with conditions.
Ergon Energy's Legacy Meter Replacement Plan sets out the planned replacement program for the legacy meters in its network.
Type
Legacy Meter Replacement Plans
On 4 December 2023 the AER granted a waiver for Ergon Energy, with conditions.
Ergon Energy Network is requesting a ring-fencing waiver in order to provide field services to Powerlink
Ergon Energy requested a ring-fencing waiver in order to continue to provide a connection to Hayman Island.