Overview

Draft decision

On 29 November 2024, we released our draft decision on Jemena Gas Networks (NSW) ('JGN') access arrangement proposal for the 2025–30 period commencing 1 July 2025.

For our draft decision, there is no Attachment 1 Services covered by the access arrangement and this component is covered in the Overview.

AER - Draft decision - JGN access arrangement 2025–30 - Overview - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 2 - Capital base - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 3 - Rate of return - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 4 - Regulatory depreciation - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 5 - Capital expenditure - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 6 - Operating expenditure - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 7 - Corporate income tax - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 8 - Efficiency carryover mechanism - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 9 - Reference tariff setting - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 10 - Reference tarff variation mechanism - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 11 - Non-tariff components - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 12 -Demand - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN access arrangement 2025–30 - Attachment 13 - Capital expenditure sharing scheme - November 2024

Authors
AER
Content type
Document

Models

Our models relating to JGN's draft decision.

AER - Draft decision - JGN 2025–30 - Capital expenditure forecast model - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN 2025–30 - Opex model - November 2024

Content type
Document

AER - Draft decision - JGN 2025–30 - PTRM - Step 2 - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN 2025–30 - RFM - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN 2025–30 - Depreciation tracking model - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN 2025–30 - Capital expenditure forecast model - November 2024

Authors
AER
Content type
Document

AER - Draft decision - JGN 2025–30 - Efficiency carryover mechanism model - November 2024

Authors
AER
Content type
Document

Consultant reports

We commissioned the following report, which we took into account when making our draft decision for JGN.

ACIL Allen - JGN demand review report - November 2024

Authors
ACIL Allen
Content type
Document

Stakeholder forum - draft decision

A public forum was held on Wednesday, 11 December 2024 at 1-2.30pm (AEDT) as an opportunity for interested stakeholders to ask questions about our draft decision.  

At the public forum we presented on our draft decision and had presentations from the Justice and Equity Centre, St. Vincent De Paul, the AER's Consumer Challenge Panel and Jemena Gas Networks. 

The combined presentation pack is published below.

AER - JGN (NSW) 2025-30 Access arrangement - Public forum - Combined slide pack - 11 December 2024

Authors
AER
Content type
Document

Submissions

-

Interested stakeholders were invited to make a submission on both our draft decision and JGN’s revised proposal. 

Submissions closed on Friday, 14 February 2025 and are available on the revised proposal page