Overview

Sector
Electricity
Segment
Distribution
Region
Victoria
Status
Historical
Commencement date
Regulatory period
-

The AER is required under chapter 6 of the National Electricity Rules to make a distribution determination for the Victorian electricity distribution network service providers (DNSPs) CitiPower, Jemena, Powercor, SP AusNet and United Energy in relation to their respective electricity distribution services.

On 30 November 2009, CitiPower, Jemena, Powercor, SP AusNet and United Energy submitted their regulatory proposals together with supporting information to the AER. The proposals cover the 2011 to 2015 regulatory period and include information on the Victorian electricity distribution network service providers' proposed capital and operating expenditure for that period.

On 24 December 2009, the AER commenced formal consultation on the regulatory proposals in accordance with the National Electricity Rules and released its final determination on 29 October 2010. The AER made a further decision on vegetation management forecast operating expenditure step change on 31 August 2012.

The AER amended CitiPower's 2011-15 distribution determination in accordance with the Tribunal’s orders of 5 April 2012. The amended 2011-15 distribution determination sets out the amount of revenue that CitiPower may recover from providing regulated electricity distribution network services.

Key Documents

Victorian distribution determination final decision 2011-2015 (29 October 2010)

Authors
AER
Content type
Document

Victorian distribution determination final decision 2011-2015 - CitiPower final determination (29 October 2010)

Authors
AER
Content type
Document

AER final decision - CitiPower and Powercor 2011-15 vegetation management forecast operating expenditure step change - August 2012

Authors
AER
Content type
Document

CitiPower distribution determination amended in accordance with the orders of the Tribunal - 28 September 2012 View details

CitiPower distribution determination amended in accordance with the orders of the Tribunal - 28 September 2012.DOC
DOC (505.5KB)
CitiPower distribution determination amended in accordance with the orders of the Tribunal - 28 September 2012 (2).pdf
PDF (471.52KB)
Authors
AER
Content type
Document