Indicative timetable

-

The AER's electricity distribution determination for Essential Energy will cover the 1 July 2029 to 30 June 2034 regulatory control period. 

An indicative timetable for the determination process is provided below. Dates are indicative and subject to change.

MilestoneDate
AER consultation on need to amend or replace the Framework and Approach (F&A)18 November 2026
AER issues decision on need to amend or replace the F&ADecember 2026
AER publishes position paper on F&AMarch 2027
AER publishes final F&AJuly 2027
Essential Energy submits its regulatory proposal to AER31 January 2028
AER publishes an issues paper and holds a public forumMarch 2028/April 2028
Submissions on regulatory proposal closeMay 2028
AER publishes draft decision on the distribution determinationSeptember 2028
AER holds a pre-determination conferenceOctober 2028
Essential Energy submits revised regulatory proposal to AERDecember 2028
Submissions on revised regulatory proposal and draft decision closeJanuary 2029
AER publishes final decision on the distribution determinationApril 2029