Project timeline

Draft decision

On 25 March 2025, we published the draft decision for the KKLP classification determination. 

Our draft decision is to classify the KKLP as a transmission pipeline. This classification takes effect from the date of publication of our final decision.

We have considered the national gas objective, the pipeline classification criterion, the pipeline characteristics outlined in section 13 of the National Gas Law and stakeholders’ views in making our draft decision.

We will make our final decision within 20 business days after submissions close.

Draft decision - Kurri Kurri Lateral Pipeline classification

Download
Authors
AER
Content type
Document

Submissions

-

Interested parties were invited to make a submission on the AER’s draft decision for the KKLP classification by 15 April 2025. We received the following submissions. 

Late submissions