Overview

Proposal

On 31 January 2018 TasNetworks submitted its regulatory proposal for the period 1 July 2019 to 30 June 2024.

View documents

Submissions

-

We invited written submissions on TasNetworks' proposal and our issues paper. Submissions closed on 16 May 2018. These submissions are available below.

View documents

Issues paper

On 28 March 2018 the AER released an issues paper highlighting some of the key elements of TasNetworks' proposal and how stakeholders can assist in our review.

AER - Issues Paper - 28 March 2018

Authors
AER
Content type
Document

Stakeholder forum

Interested parties were invited to join us for a public forum on TasNetworks' proposal on 10 April 2018 in Hobart, Tasmania.

AER - TasNetworks Public Forum Presentation - 10 April 2018

Authors
AER
Content type
Document

Consumer Challenge Panel - TasNetworks Public Forum Presentation - 10 April 2018

Authors
Consumer Challenge Panel (CCP)
Content type
Document

TasNetworks - TasNetworks Public Forum Presentation - 10 April 2018

Authors
TasNetworks
Content type
Document

Models - Distribution

TasNetworks has also submitted a distribution Service Target Performance Incentive Scheme (STPIS) model which is too large for us to publish on our website. However we can provide this model on request. Please emailemailTasNetworks2019ataer [dot] gov [dot] au (TasNetworks2019[at]aer[dot]gov[dot]au) if you want the model.

View documents

Models - Transmission

View documents

Supporting information

View documents

Regulatory information notice - Distribution

View documents

Regulatory information notice - Transmission

View documents

Expenditure forecasting methodology

TasNetworks - Cover letter to AER - Expenditure Forecasting Methodology 2019-24 - 29 June 2017

Authors
TasNetworks
Content type
Document

TasNetworks - Combined Expenditure Forecasting Methodology 2019-24 - June 2017

Authors
TasNetworks
Content type
Document

Proposed negotiated distribution service criteria

The AER has published proposed negotiated distribution service criteria for TasNetworks, which will be considered in conjunction with TasNetworks' regulatory proposal. The AER has not published Negotiated Transmission Service Criteria for TasNetworks. New National Electricity Rules commencing on 1 July 2018 remove the requirement for us to make a determination that specifies the Negotiated Transmission Service Criteria that apply to Transmission Network Service Providers..

AER - Proposed negotiated distribution service criteria for TasNetworks electricity distribution 2019-2024 - February 2018

Authors
AER
Content type
Document

Confidentiality claims - 2019-24 regulatory proposals

This table compares the proportion of confidential material in each of the 2019-24 regulatory proposals submitted to the AER, in accordance with clauses 6.9.2A and 6A.11.2A of the National Electricity Rules.

Confidentiality claims comparative table - 30 April 2018

Authors
AER
Content type
Document