On 31 May 2008, Transend submitted its revenue proposal, proposed negotiating framework and proposed pricing methodology to the AER.
Regulatory proposal
Transend Cover letter to transmission revenue proposal
Supporting information - Appendices
Proposed negotiated distribution service criteria
Under clause 6A.9.4 of the NER the AER’s transmission determination for Transend must set out the Negotiated Transmission Service Criteria (NTSC). The NTSC will be applied by Transend to negotiate the terms and conditions of access for negotiated transmission services and access charges. Negotiated transmission services include:
• connection services including entry, exit and TNSP to TNSP connection services;
• use of system services supplied by the shared transmission network that exceed or are below the networks specified performance standard under any legislation of a participating jurisdiction;
• use of system services relating to augmentation or extension for loads of the transmission network.
The NTSC will also be used by a commercial arbitrator in resolving any dispute between Transend and a person wishing to receive a negotiated transmission service.
The NTSC determined by the AER must give effect to, and be consistent with, the negotiated transmission services principles set out in clause 6A.9.1 of the NER.
AER - Proposed final decision on Transend's negotiated transmission services criteria
Stakeholder forum
The Australian Energy Regulator (AER) held a public forum on the revenue proposal submitted by Transend at the Hotel Grand Chancellor in Hobart.
Mr Andrew Reeves (AER Board Member) hosted the forum, with presentations from Transend, the Tasmanian Department of Infrastructure, Energy & Resources (DIER), Aurora Energy and the Major Employers Group.
| Milestones | Date |
|---|---|
| Receive Transend’s revenue proposal | 31 May 2008 |
| Public forum on Transend’s regulatory proposal | 6 August 2008 |
| Submissions close on the regulatory proposals | 11 August 2008 |
| Release the AER’s draft decision and consultant’s report | November 2008 |
| Public forum on the AER’s draft decision | December 2008 |
| Submissions close on the draft decision and consultant’s report | February 2009 |
| Release the AER’s final decision | April 2009 |
Please note this timeline is subject to change.
Submissions - on Transends proposal and the negotiated transmission service criteria
Submissions closed 11 August 2008.