On 13 February 2026, Transgrid applied to the AER to revoke and substitute its electricity transmission revenue determination for the 2023–28 regulatory control period, to adjust total forecast capital expenditure (capex) approved for Project EnergyConnect (PEC) in our April 2023 final decision

On 1 September 2026, we published a consultation paper setting out our preliminary position on Transgrid’s application to reopen the 2023–28 transmission revenue determination for Project EnergyConnect. While this is not a legislated requirement for the reopener process, we consider that all stakeholders should have the opportunity to engage with our preliminary views. We invite stakeholders to make submissions on our consultation paper by 1 October 2026. Written submissions or requests to make a submission via alternative methods should be emailed to: aerinquiryataer [dot] gov [dot] au.

Consultation paper

-

On 1 September, we published a consultation paper setting out our preliminary position on Transgrid’s application to reopen its 2023–28 transmission revenue determination for Project EnergyConnect.

Invitation for submissions

We invite stakeholders to make submissions on our consultation paper by 1 October 2026. Written submissions or requests to make a submission via alternative methods should be emailed to: aerinquiryataer [dot] gov [dot] au.

Consultation paper - AER preliminary position on Transgrid’s application to reopen the 2023–28 transmission revenue determination for Project EnergyConnect

Authors
AER
Content type
Document

Transgrid's application

On 13 February 2026, Transgrid applied to the AER to revoke and substitute its electricity transmission revenue determination for the 2023–28 regulatory control period, to adjust total forecast capital expenditure (capex) approved for Project EnergyConnect (PEC) in our April 2023 final decision.

Project EnergyConnect - An application to reopen the 2023-2028 Revenue Determination - Transgrid - 20260213

Authors
Transgrid
Content type
Document

Transgrid's supporting material

Transgrid has submitted the following materials in support of its reopener application.

View documents

Submissions on Transgrid's application

-

We invited energy consumers and other interested parties to make submissions on Transgrid’s reopener application. Submissions closed on 28 April 2026. 

View documents

AEMO correspondence

We sought advice from Australian Energy Market Operator (AEMO) on the implications of PEC on system security and reliability in New South Wales and South Australia.

AER letter to AEMO - advice on Project Energy Connect system security

Authors
AER
Content type
Document

AEMO letter to Clare Savage AER RE - System security and reliability in relation to Project EnergyConnect 2026.06.01

Authors
Australian Energy Market Operator (AEMO)
Content type
Document

AER letter to AEMO - follow up advice on Project EnergyConnect system security

Authors
AER
Content type
Document

AEMO letter to Clare Savage AER RE - follow up advice on system security and reliability in relation to Project EnergyConnect 2026.06.26

Authors
Australian Energy Market Operator (AEMO)
Content type
Document