TransGrid - Determination 2018-23

  • Accepting submissions
Sector: 
Segment: 
Commencement date: 
13 November 2015
Regulatory period: 
1 July 2018 to 30 June 2023
(5 years)
Status: 
Contact: 
General inquiries - TransGrid transmission determination TransGrid2018@aer.gov.au
AER reference: 
58709

Overview

The AER is required to determine the revenue allowance for TransGrid for the regulatory control period commencing 1 July 2018 and finishing on 30 June 2023.

On 31 January 2017, TransGrid submitted its transmission revenue proposal and supporting information to the AER. The proposal sets out the revenue TransGrid proposes to collect from electricity consumers through transmission charges from 2018 to 2023.

On 28 September 2017, we released our draft decision on TransGrid's transmission determination for the 2018–23 regulatory control period.

Submissions

We invite energy consumers and other interested parties to make submissions on our draft decision by close of business on Friday 12 January 2018 to TransGrid2018@aer.gov.au.

Stakeholder forum

We held a pre-determination conference on 10 October 2017 in Sydney to discuss our draft decision with stakeholders. The slide presentations from the AER, TransGrid and the Consumer Challenge Panel are available under the draft decision milestone.