On 30 April 2015, the AER released its final decision on TransGrid’s transmission determination for the 2015–18 period.

Update

On 15 December 2017 the AER wrote to TransGrid setting out how it proposed to correct a mathematical error in the inflation calculation in its 3 July 2015 decision.

Subject to considering submissions on our proposed correction, the AER is proposing to revoke the 3 July 2015 determination and substitute it with a new determination to correct the identified error under clause 6A.15 of the NER by no later than 1 March 2018.

Background

On 20 May 2015 the AER wrote to TransGrid setting out how it proposed to correct a small number of administrative errors in its 30 April determination. This is to ensure that the associated legal documents accurately reflect its decision.

On 3 July 2015 the AER decided to revoke its final determination and publish substitute versions of the transmission determination, overview and the attachments affected by these administrative errors.

On 28 March 2014, the AER released its transitional determination for TransGrid for the transitional regulatory control period 2014-15.

Key Documents

AER - Rate of return - Fact sheet - April 2015 View details

AER - Rate of return - Fact sheet - April 2015_3.pdf
PDF (261.61KB)
AER - Rate of return - Fact sheet - April 2015_3.DOCX
DOCX (78.46KB)
Authors
AER
Content type
Document

AER - Final decision TransGrid transmission determination - Fact sheet - April 2015 View details

AER - Final decision TransGrid transmission determination - Fact sheet - April 2015_0.docx
DOCX (303.88KB)
AER - Final decision TransGrid transmission determination - Fact sheet - April 2015.pdf
PDF (407.35KB)
Authors
AER
Content type
Document

Letter from AER to TransGrid advising of revocation and substitution - 3 July 2015

Authors
AER
Content type
Document

AER - Final decision (Substitute) TransGrid transmission determination - Overview - July 2015 View details

AER - Final decision (Substituted) TransGrid transmission determination - Overview - July 2015.docx
DOCX (590.6KB)
AER - Final decision (Substituted) TransGrid transmission determination - Overview - July 2015.pdf
PDF (1.01MB)
Authors
AER
Content type
Document

Letter from AER to TransGrid about correcting errors in inflation calculation

Authors
AER
Content type
Document