| Milestone | Date | 
|---|---|
| AER published preliminary position F&A for Directlink | March 2018 | 
| Submissions on preliminary F&A for Directlink closed | 27 April 2018 | 
| AER published final F&A for Directlink | July 2018 | 
| Directlink submitted regulatory proposal to AER | 31 January 2019 | 
| AER publishes issues paper | 28 March 2019 | 
| AER holds public forum | 9 April 2019 | 
| Submissions on regulatory proposal close | 16 May 2019 | 
| AER to publish draft transmission determination | 8 October 2019 | 
| AER to hold a predetermination conference | October 2019 | 
| Directlink to submit revised regulatory proposal to AER | December 2019 | 
| Submissions on revised regulatory proposals and draft decision close | January 2020* | 
| AER to publish transmission determination for regulatory control period | 5 June 2020 | 
Notes:
	* The NER does not provide specific timeframes in relation to publishing draft decisions. Accordingly, this date is indicative only.