Revenue Proposal

On 29 November 2024, Marinus Link Proprietary (Pty) Limited (Ltd) submitted its Stage 1, Part B (Construction Cost) revenue proposal to the AER.

Marinus Link - ML-B-002 MLPL Revenue Proposal Stage 1 - Part B (Construction) - December 2024

Authors
Marinus Link
Content type
Document

Confidentiality claims

Marinus Link - ML-B-015 Confidentiality Claims - December 2024

Authors
Marinus Link
Content type
Document

Supporting information

View documents

Consultant reports

Marinus Link - ML-B-008 Attachment 6 - Explanation of Capital Expenditure Requirements - Hedging (Chatham Financial) - December 2024

Content type
Document

Marinus Link - ML-B-009 Attachment 7 - Explanation of Capital Expenditure Requirements - Risk Allowance (E3) - December 2024

Content type
Document

Marinus Link - ML-B-010 Attachment 8 - Electricity-Related Labour and Materials Escalation Costs (Oxford Economics Australia) - December 2024

Authors
BIS Oxford Economics
Content type
Document

Marinus Link - ML-B-011 Attachment 9 - Independent Verification of MLPL costs (Aurecon Advisory) - December 2024

Authors
Aurecon Australasia Pty Ltd
Content type
Document

Issues Paper

On 21 March 2025, we published our Issues Paper on the Marinus Link Pty Ltd Stage 1, Part B (Construction Costs) revenue proposal.  

Submissions on our Issues Paper closed on 18 April 2025.

AER - Issues Paper - Marinus Link Stage 1 Part B (Construction Costs) - March 2025

Authors
AER
Content type
Document

Stakeholder forum

Consumer engagement is a valuable input to our determination. Stakeholders can inform our process by providing their views on aspects of the proposal.

On 3 April 2025, we hosted an online public forum to provide stakeholders the opportunity to ask questions about Marinus Link's proposal and our Issues Paper. Presentations were delivered by Marinus Link and the AER. The presentation slides and responses to questions raised during the public forum are available below.

AER - Public Forum - Marinus Link Stage 1, Part B (Construction costs) proposal - April 2025

Authors
AER
Marinus Link
Content type
Document

AER - Public Forum - Marinus Link Stage 1, Part B (Construction costs) proposal stakeholder questions - April 2025

Authors
AER
Marinus Link
Content type
Document

Submissions

-

Submissions in response to the revenue proposal and Issues Paper closed on 18 April 2025. The following submissions were received.

View documents

Marinus Link request for FID Guidance

On 20 February 2025, Marinus Link Pty Ltd wrote to the AER requesting guidance to support a Financial Investment Decision. The letter and the AER's response are available below.

Marinus Link - Letter to AER - Guidance to support FID - February 2025

Authors
Marinus Link
Content type
Document

AER CEO Letter - Response to FID Guidance Request - April 2025

Authors
AER
Content type
Document