On 31 July 2025, we received a compliant revenue proposal from Transgrid for the Enabling Central-West Orana (CWO) Renewable Energy Zone Network Infrastructure Project (CWO Enabling Project).
On 20 October 2025, we published our preliminary position paper which provides an early indication of our assessment of Transgrid’s revenue proposal. It identifies the key areas of focus which we consider require most stakeholder attention in making our final decision.
On 22 January 2026, we made our final decision for the CWO Enabling Project, within the required 126 day timeframe. Consistent with the requirements of clause 53(4) of the EII Regulation, we will be publish our final decision as soon as reasonably practicable once we receive notification from EnergyCo that financial close has been achieved for the CWO Enabling Project.