Overview

Annual adjustment

-

The AER made the System Integrity Protection Scheme Service (SIPS) battery service revenue determination for Transgrid under the Electricity Infrastructure Investment Act 2020 (NSW) on 14 December 2022. This revenue determination included adjustment events/mechanisms that allow for changes to the schedule of payments to be paid to Transgrid over the project term.

On 31 March 2026, Transgrid submitted to the AER a revenue adjustment proposal to reflect the occurrence of adjustment event - Delay in achieving Commercial Operation. This results in a reduction to the amount payable to Transgrid over the project term triggered by a delay in achieving the Commercial Operation Date for the battery service.

We have assessed the revenue adjustment proposal in accordance with the Electricity Infrastructure Investment Regulation 2021 (NSW) and are satisfied that:

  • the trigger for the adjustment event has occurred,
  • the proposal accurately calculates the adjustment to be applied to the schedule of payments, and
  • the adjustment has been carried out in accordance with our Revenue determination guideline for NSW contestable network projects (Guideline) and the contractual arrangements entered into by Transgrid. 

Therefore, we have reduced the amount payable to Transgrid under the SIPS battery service revenue determination

We have decided not to publish the updated schedule of payments consistent with our previous decisions on the Waratah Super Battery project. However, we will publish an update of the aggregated revenue for the contestable components of the Waratah Super Battery project in May 2026.

Transgrid - Revenue adjustment proposal - Waratah Super Battery project - SIPS battery service - 31 March 2026