Overview

Draft decision

On Thursday 28 January 2016 the AER Board made a draft decision to grant a temporary and conditional ring fencing waiver for Energex's BESS domestic pilot project. We will release a final decision in due course.

Energex ring fencing waiver application - AER Draft decision - January 2016

Authors
AER
Content type
Document

Submissions - on the AER's draft decision on Energex's ring fencing waiver application

-

Submissions on the AER's draft decision on Energex's ring fencing waiver application closed on 19 February 2016.

Origin Energy - Submission on AER draft decision on Energex's ring fencing waiver application - 19 February 2016

Authors
Origin Energy
Content type
Document