Final decision

On 30 April 2024, we released our final decision on Ausgrid's electricity distribution determination for the 2024–29 regulatory control period. 

Our final decision is set out in the Overview and accompanying attachments. As a number of issues were settled at the draft decision stage or required only minor updates, we have not prepared all attachments.

In these circumstances our draft decision reasons form part of this final decision.

AER - Final Decision - Overview - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 1 - Annual revenue requirement - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 2 - Regulatory asset base - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 4 - Regulatory depreciation - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 5 - Capital expenditure - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 6 - Operating expenditure - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 7 - Corporate income tax - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 12 - Customer Service Incentive Scheme - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 13 - Classification of services - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 14 - Control mechanisms - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 15 - Pass through events - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Content type
Document

AER - Final Decision Attachment 16 - Alternative control services - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 18 - Connection policy - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 19 - Tariff structure statement - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

AER - Final Decision Attachment 20 - Metering services - Ausgrid - 2024–29 Distribution revenue proposal - April 2024

Authors
AER
Content type
Document

Tariff Structure Statement and Explanatory Statements

Distributors in NSW are the first to introduce export reward tariffs in their 2024-29 TSSs. The Export reward tariffs and you (factsheet) has been created to read alongside our TSS decisions.

Final Decision - Ausgrid distribution determination 2024–29 - Revised Tariff Structure Statement - April 2024 - Clean

Content type
Document

Final Decision - Ausgrid distribution determination 2024–29 - Revised Tariff Structure Statement - April 2024 - Marked Up

Content type
Document

Final Decision - Ausgrid distribution determination 2024–29 - Revised Tariff Structure Explanatory Statement - April 2024 - Clean

Content type
Document

Final Decision - Ausgrid distribution determination 2024–29- Revised Tariff Structure Explanatory Statement - April 2024 - Marked Up

Content type
Document

Models

The following models relate to Ausgrid's final decision.

AER - Final decision - Ausgrid distribution determination 2024-29 Standardised SCS Capex Model - April 2024

Authors
AER
Content type
Document

AER – Final decision – Ausgrid distribution determination 2024-29 - CESS distribution model - April 2024

Authors
AER
Content type
Document

AER – Final decision – Ausgrid distribution determination 2024-29 - CESS transmission model - April 2024

Authors
AER
Content type
Document

AER – Final decision – Ausgrid distribution determination 2024-29 – Opex model – April 2024

Authors
Ausgrid
Content type
Document

AER – Final decision – Ausgrid distribution determination 2024-29 – EBSS model – April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - PTRM - Distribution - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - PTRM - Transmission - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - RFM - Distribution - April 2024

Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - RFM - Transmission - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - Depreciation module - Distribution - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - Depreciation module - Transmission - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - Public lighting - pre-2009 fixed charge model - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 - Public lighting model - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 -Att. 9.5 - Standardised ANS model - 30 Nov 2023

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024-29 STPIS model - April 2024

Authors
Ausgrid
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024–29 - Metering RFM - April 2024

Authors
AER
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024–29 - Metering expenditure model - April 2024

Authors
AER
Content type
Document

AER - Final decision - Ausgrid distribution determination 2024–29 - Metering PTRM - April 2024

Authors
AER
Content type
Document

Consultant reports

We commissioned the following report, which we took into account when making our final decision for Ausgrid. 

AER - Final Decision - Ausgrid 2024-29 - KPMG - Wage price index forecasts - April 2024

Authors
KPMG
Content type
Document