Overview

Draft decision

On 20 July 2016, we released our draft decision on AusNet Services' transmission determination for the 2017–22 regulatory control period.

We also released a fact sheet to accompany and summarise our draft decision.

View documents

Consultant reports

The AER commissioned a number of reports that it took into account when making its draft decision.

Economic Insights - Memo on transmission multilateral total factor productivity results - 29 April 2016

Authors
Economic Insights Pty Ltd
Content type
Document

Lally, Dr. Martin - Gamma and the Australian Competition Tribunal Decision - 23 May 2016

Authors
Dr Martin Lally
Content type
Document

Partington and Satchell - Advice to the AER on cost of equity issues in 2016 electricity and gas determinations - April 2016

Authors
Partington and Satchell
Content type
Document

Partington and Satchell - Report to the AER - Discussion of the allowed cost of debt - 5 May 2016

Authors
Partington and Satchell
Content type
Document

Models

The AER must publish certain models with its draft decision for AusNet Services.

View documents

Submissions

-

We invited interested parties to respond to our draft decision by providing us with written submissions by 21 September 2016. View the submissions received on the draft decision.

Stakeholder forum

On 9 August 2016 the AER held a public forum on the draft decision.

AER - Public forum agenda - AER draft decision for AusNet transmission - August 2016

Authors
AER
Content type
Document

AER - AusNet Services (transmission) draft decision public forum presentation - 9 August 2016

Authors
AER
Content type
Document

CCP - AusNet Services (transmission) draft decision public forum presentation - 9 August 2016

Authors
Consumer Challenge Panel (CCP)
Content type
Document

AusNet Services - AER transmission draft decision public forum presentation - 9 August 2016

Authors
AusNet Services
Content type
Document