| Indicative dates for key milestones in the decision-making process | |
|---|---|
| Milestone | Date* | 
| AER consultation on need to amend or replace the Framework and Approach (F&A) | 14 November 2023 | 
| AER issues decision on need to amend or replace the F&A | 14 December 2023 | 
| AER publishes position paper on F&A | 16 March 2024 | 
| AER publishes F&A for CitiPower | by 31 July 2024 | 
| CitiPower submits its regulatory proposal to AER | 31 January 2025 | 
| AER publishes an issues paper and holds a public forum | March/April 2025** | 
| Submissions on regulatory proposal close | May 2025 | 
| AER publishes draft determination decision | by 30 September 2025 | 
| AER holds a pre-determination conference | October 2025 | 
| CitiPower submits revised regulatory proposal to AER | December 2025 | 
| Submissions on revised regulatory proposal and draft decision close | January 2026 | 
| AER publishes distribution determination for regulatory control period | by 30 April 2026 | 
* This is an indicative timetable and is subject to change.
** The date provided is based on the AER receiving compliant proposals. The date may be altered if we receive non-compliant proposals.