Regulatory proposal

On 30 January 2026, Powerlink submitted its transmission regulatory proposal for the period 1 July 2027 to 30 June 2032 (2027-32). This submission and supporting materials are included below.

Powerlink - 2027-32 Revenue Proposal - January 2026

Authors
Powerlink Queensland
Content type
Document

Powerlink - 2027-32 Revenue Proposal Overview - January 2026

Authors
Powerlink Queensland
Content type
Document

Powerlink - 2027-32 Regulatory Proposal Cover Letter - January 2026

Authors
Powerlink Queensland
Content type
Document

Powerlink - 2027-32 - Cost Allocation Methodology - August 2008

Content type
Document

Confidentiality claims

Powerlink - 2027-32 Confidentiality Register - January 2026

Authors
Powerlink Queensland
Content type
Document

Regulatory information notice

View documents

Models

View documents

Appendices

View documents

Supporting information

View documents

Supporting information - Project packs

View documents

Issues paper

On 30 March 2026, the AER published an Issues paper for public consultation. The Issues paper highlights the key elements of Powerlink's transmission revenue proposal and identifies issues that are likely to be a focus of the AER’s assessment and engagement with stakeholders. 

AER - Issues paper - Powerlink electricity transmission determination 2027-32 - March 2026

Authors
AER
Content type
Document

Submissions - Regulatory Proposal

-

We invited stakeholders to make submissions on Powerlink’s 2027-32 electricity transmission revenue proposal and our Issues Paper by Wednesday, 13 May 2026. 

View documents

Stakeholder forum

Consumer engagement is a valuable input to the AER's determination. Stakeholders can assist in this process by providing their views on aspects of Powerlink’s transmission revenue proposal. 

On 9 April 2026, the AER hosted an online public forum regarding Powerlink's 2027-32 transmission revenue proposal and the AER's Issues paper.

AER Public Forum - Powerlink 2027-32 transmission revenue proposal - Presentation slides

Content type
Document

Updates

On 30 June 2026, Powerlink provided an update to their Appendix 4.04 - Contingent Projects attachment. The updated attachment is available below.

Powerlink - 2027-32 - Appendix 4.04 - Contingent Projects (Updated) - June 2026

Authors
Powerlink Queensland
Content type
Document