- Upcoming stakeholder forum
- Accepting submissions
Overview
Draft decision
On 28 September 2023 we released our draft decision for Ausgrid's revenue determination for the 2024–29 period, commencing 1 July 2024. Ausgrid now has until 30 November 2023 to respond to the respective draft decisions in a revised proposal.
A joint online public forum will be held for NSW distributors (Ausgrid, Endeavour Energy and Essential Energy) on 9 October 2023. Registrations can be made at Eventbrite.
Interested stakeholders are invited to provide written submissions on the draft decisions and revised proposals by 19 January 2024.
Ausgrid's proposal
On 31 January 2023 Ausgrid submitted its 2024–29 Regulatory Proposal to the AER. The proposal sets out the revenue Ausgrid proposes to collect from its consumers through distribution network charges over the 2024–29 regulatory control period.
On 28 March 2023, the AER published an Issues Paper highlighting some of the key elements of Ausgrid's proposal.
A public forum for interested parties was held on 5 April 2023, we have published the joint presentation pack.
Submissions on Ausgrid's 2024–29 Regulatory proposal, our Issues Paper, and our proposed Negotiated distribution service criteria closed on 12 May 2023 and are now available on the website.
Background
Ausgrid is an electricity distribution network service provider. Its next five year regulatory control period commences on 1 July 2024 to 30 June 2029 (2024–29).
Under the NER, Ausgrid is required to submit its regulatory proposal to us by 31 January 2023. However, prior to that date, the NER require us to review the current F&A paper that applies to Ausgrid and decide whether to amend or replace it.