Update
Back to topOn 1 April 2020, Ausgrid informed the AER that they would not be able to provide a punctual annual pricing proposal for its New South Wales distribution network for the period 1 July 2020 to 30 June 2021. Ausgrid has advised that they intend to provide an annual pricing proposal by 17 April 2020.
Documents (1) | Author |
---|---|
Ausgrid - Letter to AER re late pricing proposal - April 2020 ( PDF 137.35 KB ) | Ausgrid |
Pricing proposal
Back to topOn 17 April 2020, Ausgrid submitted to the AER an annual pricing proposal for its New South Wales distribution network for the period 1 July 2020 to 30 June 2021. Ausgrid’s pricing proposal will be assessed for compliance with the AER's 2019-24 regulatory determination.
On 5 May 2020, Ausgrid resubmitted their proposal in response to AER's queries.