On 4 August 2025, we formally started our 2026 Rate of Return Instrument (RORI) review with the release of an AER discussion paper.

The discussion paper set out our positions on what we considered were likely to be the key issues for the 2026 RORI review. It formed part of our initial engagement for the review, building on previous reviews and stakeholder engagement. We invited stakeholder input on the proposed areas of focus and our approach to further analysis by 19 December 2025.

AER – 2026 Review Discussion Paper – 4 August 2025

Authors
AER
Content type
Document

AER – 2026 RORI review discussion paper – Appendix A – WTA illustrative example – 4 August 2025

Authors
AER
Content type
Document

Preliminary sample of international firms tickers

Content type
Document

Stakeholder forum

The AER held an online public forum on the 2026 RORI review discussion paper on 26 August 2025. Presentations from the forum are provided below.

AER - 2026 RORI review public forum presentation - 26 August 2025

Authors
AER
Content type
Document

ENA - 2026 RORI review public forum presentation - 26 August 2025

Authors
ENA
Content type
Document

ECA - 2026 RORI review public forum presentation - 26 August 2025

Authors
ECA
Content type
Document

Early submissions

On 25 July 2024, we received an unsolicited consultant report commissioned by the ENA and prepared by CEG on the use of international comparators to estimate equity beta. We met with the ENA and CEG on 25 November 2024 and sought clarifications on aspects of the report. The ENA and CEG responded to our questions in writing on 17 December 2024.

ENA - CEG Report Using international comparators to estimate the benchmark Australian equity beta - July 2024

Content type
Document

ENA - CEG Report Appendix A firm profile - July 2024

Content type
Document

ENA - CEG Response to AER questions On CEG 2022 and 2024 reports - December 2024

Content type
Document

ENA - CEG Response Appendix A firm profile with analysis - December 2024

Content type
Document

Submissions

We invited interested stakeholders to make a consolidated submission on both the AER’s discussion paper and the Eligible Experts’ report. Submissions closed on 19 December 2025.

Stakeholders’ submissions informed the AER’s considerations for the draft 2026 RORI which we published on 29 May 2026.

View documents