On 28 September 2023, we released our draft decisions on TasNetworks' electricity distribution and transmission determinations for the 2024-29 period.
On this page
Draft decision
AER - Draft Decision Overview - TasNetworks - 2024-29 Distribution and Transmission revenue proposal - September 2023
Draft decision - distribution attachments
We have now published our draft decision on TasNetworks electricity distribution determination for the 2024-29 regulatory control period.
Draft decision - transmission attachments
We have now published our draft decision on TasNetworks electricity transmission determination for the 2024-29 regulatory control period.
Models - Distribution
Our models relating to TasNetworks draft decision.
Models - Transmission
Our models relating to TasNetworks draft decision.
Consultant reports
We commissioned the following reports, which we took into account when making our draft decision for TasNetworks.
AER - TasNetworks 2024-29 - Draft Decision - KPMG - Wage price index forecasts - August 2023
EMCa - TasNetworks 2024 to 2029 Regulatory Proposal Review of proposed expenditure on ICT cyber security
Stakeholder forum - Pre-determination conference
On 10 October 2023, we hosted an online pre-determination conference for TasNetworks to discuss our draft decision.
The presentation for this forum is available below.
AER - Predetermination Conference TasNetworks Presentation pack - 10 October 2023
Submissions
Interested stakeholders were invited to make a submission on both our draft decision and TasNetworks' electricity distribution and transmission determinations revised proposals.
Submissions closed on Friday, 19 January 2024 and are available on the Consultation milestone.
Update
The AER has provided guidance to distributors on the treatment and classification of legacy metering services in light of the final outcome of the AEMC's review of the regulatory framework for metering services. This guidance should be considered in preparing upcoming regulatory submissions.