ElectraNet - Determination 2018-23

Sector: 
Segment: 
Commencement date: 
28 March 2016
Regulatory period: 
1 July 2018 to 30 June 2023
(5 years)
Status: 
Contact: 
General inquiries - ElectraNet determination ElectraNet2018@aer.gov.au
AER reference: 
58711

Overview

The AER is required to determine the revenue allowance for ElectraNet for the five year regulatory control period commencing 1 July 2018.

On 28 March 2017, ElectraNet submitted its transmission revenue proposal and supporting information to the AER. The proposal sets out the revenue ElectraNet proposes to collect from electricity consumers through transmission charges from 1 July 2018 to 30 June 2023.

On 25 May 2017, we published an issues paper on ElectraNet's revenue proposal.

On 7 June 2017, we conducted a public forum on ElectraNet's revenue proposal.

We invited submissions from interested parties on ElectraNet's revenue proposal and our issues paper. Submissions closed on 7 July 2017.

Stakeholder forum

The AER held a public forum in Adelaide on 7 June 2017 on ElectraNet's revenue proposal. The presentation slides are available on our website.