Overview

Revised proposal

On 3 July 2015, SA Power Networks submitted its revised regulatory proposal to the AER's preliminary decision.

SA Power Networks - Cover letter to revised regulatory proposal - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - 2015-20 Revised Regulatory Proposal - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - A.1 RRP Confidentiality Claim v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - A.2 RRP Directors Certification v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - C.1 Banarra - Final Gap Analysis Assessment - July 2015

Authors
Banarra
Content type
Document

SA Power Networks - C.2 NTF Review of SACOSS-CBR Research - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - C.3 NTF Review of Business SA - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - C.4 NTF Review of CCP2 Comments - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - C.5 NTF Response to SACOSS’ WTP Assertions - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - C.6 NTF Review of AER Response - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - C.7 NTF Review of Oakley Greenwood - July 2015

Authors
The NTF Group
Content type
Document

SA Power Networks - G.1a Kangaroo Island Submarine cable add information - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.2 Bushfire mitigation – Support Evidence v1.0

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.3 Risk Spatial Bushfire Risk Report v1.0 Redacted

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.4 Metered mains supporting evidence v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.5 Protection compliance Backup - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.6 Reliability Hardening the network - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.7 Reliability Low reliability feeders - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.8 Reliabiity Poorly served communities - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.9 Reliability Micro-grid trial - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.10a DGA Revised ADMS and ZSS v1.0 - July 2015

Authors
DGA Consulting
Content type
Document

SA Power Networks - G.12a Voltage Monitoring in the LV network v1.1

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.12b Voltage Monitor in the LV network model V1.0

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.13 KPMG IT Review Redacted - July 2015

Authors
KPMG
Content type
Document

SA Power Networks - G.14 IT Resourcing and Deliverability v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.15 IT Field Force Mobility Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.16 IT Enterprise Asset Management Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.17 IT Data Centre Opex Step Change - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.19 IT RIN Reporting Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.20 IT SAP Foundations Opex Step Change - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.21 IT CISOV CRM Opex Step Change Rep Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.22 IT EAM and RIN Reporting Paper - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.23 IT Project Portfolio Management Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.24 IT Benefits - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.25 Telecommunications Network Operations Centre Business Case - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.27 Revised SCS CAPEX SEM - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.1 Frontier Review of AER's Preliminary Decision on Labour Escalation Rates

Authors
Frontier Economics
Content type
Document

SA Power Networks - H.2 Frontier Review of AER's Preliminary Decision on Labour Escalation Rates v1.0

Authors
Frontier Economics
Content type
Document

SA Power Networks - H.3 Skills Shortages in SA Power Networks

Authors
SA Power Networks
Content type
Document

SA Power Networks - G.18 IT Info Security Bus Case Step Change - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.4 BIS Shrapnel Utilities Sector Wage Forecasts to 2019-20

Authors
BIS Shrapnel
Content type
Document

SA Power Networks - H.5 Opex Step Changes – No Access Poles v1.0 Redacted

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.6 Bushfire Safety – Opex SC Inspect Cycle v1.0 - Copy

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.7 Distribution Network Pricing Rules - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.7a Distribution Network Price Rules Cost Est - Appendix - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.8 Competition in Metering Rule Change - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.8a Meter Rule Cost Estimations - Appendix A - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - H.10 GHD Vegetation Management Bushfire Program - July 2015

Authors
GHD
Content type
Document

SA Power Networks - H.11 NERA Funding Projects that provide Customer Benefits v1.0

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - H.12 Revised SCS OPEX SEM - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - L.1 Roll Forward Model SCS - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - L.2 Roll Forward Model ACS - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - L.3 Roll Forward Model Schedules - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - M.1 RBA Speech 21 April 2015 v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - M.2 NERA Sharpe-Lintner CAPM and Fama-French 3 Factor Model - March 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.3 SFG Foundation Model Approach of the AER - Estimating Cost of Equity - March 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.4 SFG Return on Equity for the Benchmark efficient entity - February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.5 NERA Historical Estimates of the Market Risk Premium - February 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.6 NERA Empirical Performance -Sharpe-Lintner & Black CAPM - February 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.7 SFG Beta & Black Capital Asset Pricing Model - 13 February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.8 SFG Fama-French model estimate required Return on Equity - February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.9 SFG Share Prices, the Divident Discount Model & the Cost of Equity for the Market & a Benchmark Energy Network - 18 February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.10 Grant Samuel Letter to the Directors of Transgrid - 12 January 2015

Authors
Grant Samuel
Content type
Document

SA Power Networks - M.11 Incenta Update on the Required Return on Equity from Independent expert reports - February 2015

Authors
Incenta Economic Consulting
Content type
Document

SA Power Networks - M.12 Frontier Key issues in Estimating Return on Equity for the Benchmark efficient entity - June 2015

Authors
Frontier Economics
Content type
Document

SA Power Networks - M.13 Frontier Review - AER conceptual analysis for equity beta - June 2015

Authors
Frontier Economics
Content type
Document

SA Power Networks - M.14 NERA The Cost of Equity Response to AER's Final Decisions for NSW & ACT & Jemena - June 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.15 NERA Assessment Historical Estimates of the Market Risk Premium - June 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.16 MALKO Dr Robert Malko Statement 16 June 2015 - July 2015

Authors
Malko Energy Consulting
Content type
Document

SA Power Networks - M.17 KNECHT Ronald L. Knecht Statement 19 June 2015 - July 2015

Authors
Ronald L Knecht
Content type
Document

SA Power Networks - M.18 SFG Updated estimate of Required Return on Equity Report - 19 May 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.19 SFG Estimating Gamma for Regulatory Purposes - February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.20 NERA Estimating distribution and redemption rates from taxation statistics - March 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.21 Frontier An appropriate regulatory estimate of gamma - June 2015

Authors
Frontier Economics
Content type
Document

SA Power Networks - M.22 NERA Estimating Distribution & Redemption Rates: Response to AER'a Final Decision NSW & ACT & Jemena - 22 June 2015

Authors
NERA Economic Consulting
Content type
Document

SA Power Networks - M.23 SFG Return on debt transition arrangements under the NGR and NER - 27 February 2015

Authors
Strategic Finance Group (SFG Consulting)
Content type
Document

SA Power Networks - M.24 CEG Critique of the AER’s JGN Draft Decision on the cost of debt - April 2015

Authors
Competition Economists Group (CEG)
Content type
Document

SA Power Networks - M.25 SCHLOGL AER JGN Draft Decision cost of debt - review of the critique by the CEG - 20 April 2015

Authors
Competition Economists Group (CEG)
Content type
Document

SA Power Networks - M.26 CEG Transition to trailing average Rate of Return on Debt, Assessment and calculations for SAPN - June 15

Authors
Competition Economists Group (CEG)
Content type
Document

SA Power Networks - M.27 CEG Extrapolation of the Bloomberg curve to 10 years - 19 June 2015

Authors
Competition Economists Group (CEG)
Content type
Document

SA Power Networks - M.28 CEG Measuring expected inflation for the PTRM - June 2015

Authors
Competition Economists Group (CEG)
Content type
Document

SA Power Networks - M.29 Frontier Cost of equity estimates over time v1.0

Authors
Frontier Economics
Content type
Document

SA Power Networks - M.30 WACC Supporting Documents List v1.0 - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - N.1 Houston Kemp - Depreciation Report - July 2015

Authors
HoustonKemp
Content type
Document

SA Power Networks - N.2 Regulatory Asset Register -SCS - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - P.1 Revised Post Tax Revenue Model -SCS - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.2 Modelling Overview - ACS Redacted - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.4 Revised ACS Capex SEM - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.6 Revised ACS Opex forecast Redacted - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.7 Revised ACS Opex SEM - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.8 Revised ACS Metering Pricing Model Redacted

Authors
SA Power Networks
Content type
Document

SA Power Networks - Q.9 Revised ACS Post Tax Revenue Model - July 2015

Authors
SA Power Networks
Content type
Document

Regulatory information notice

SA Power Networks - Confidentiality Template - Revised Reset 2015-20 data information - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Revised Proposal RIN Overview - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - REVISED RESET RIN 2015-20 PUBLIC - July 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - RP RESET RIN - TAB 2.1 Attachment A - Balancing Items Reconciliation - July 2015

Authors
SA Power Networks
Content type
Document

Supporting information

AER - SA Power Networks unpublished supporting material - July 2015 View details

AER - SA Power Networks unpublished supporting material - July 2015.docx
DOCX (334.95KB)
AER - SA Power Networks unpublished supporting material - July 2015.pdf
PDF (231.1KB)
Authors
AER
Content type
Document

Submissions

-

On 3 July 2015, SA Power Networks submitted its revised regulatory proposal. Submissions on SA Power Networks' revised proposal closed on  24 July 2015.

Almond Co Australia - Submission on SAPN's revised regulatory proposal - 8 July 2015

Authors
AlmondCo Australia
Content type
Document

Business SA - Submissions re SA Power Networks Determination 2015-2020 - 20 July 2015

Authors
Business SA
Content type
Document

Century Orchards - Submission to SA Power Networks Revised Regulatory Proposal - 9 July 2015

Authors
Century Orchards
Content type
Document

CitiPower/Powercor - Submission in relation to the current regulatory determination processes (with 5 attachments) - 24 July 2015

Authors
Powercor Australia
CitiPower
Content type
Document

CitiPower/Powercor - Attachment 1 - Steady state example - 24 July 2015

Authors
Powercor Australia
CitiPower
Content type
Document

CitiPower/Powercor - Attachment 2 - Price trend example (applying baseline method) - 24 July 2015

Authors
Powercor Australia
CitiPower
Content type
Document

CitiPower/Powercor - Attachment 3 - Letter to AER re SAPN Revised Proposal: Depreciation - 24 July 2015

Authors
Powercor Australia
CitiPower
Content type
Document

CitiPower_Powercor - Attachment 4 - Incenta final report - calculation of straight line depreciation - 24 July 2015

Authors
Incenta Economic Consulting
Content type
Document

CitiPower/Powercor - Attachment 5 - Federal Energy Regulatory Commission - Opinion no. 531 - 24 July 2015

Authors
Powercor Australia
CitiPower
Content type
Document

City of Marion - Submission to SA Power Networks - Determination 2015-2020 - 28 July 2015

Authors
City of Marion
Content type
Document

District Council of Elliston - Submission to SA Power Networks - Revised Regulatory Proposal - 17 July 2015

Authors
District Council of Elliston
Content type
Document

Flinders Ranges Council - Reliability of electricity in Hawker, South Australia - 16 July 2015

Authors
Flinders Ranges Council
Content type
Document

Jemena - Submission on recent proposals made by SAPN, AGN, AAD, Energex and Ergon Energy - 24 July 2015

Authors
Jemena
Content type
Document

John Herbst - Submission to the AER on SA Power Networks Revised Regulatory Proposal 2015-2020 - 24 July 2015

Authors
John Herbst
Content type
Document

Jubilee Almonds - Submission to SA Power Networks Revised Regulatory Proposal - 10 July 2015

Authors
Jubilee Almonds
Content type
Document

Multinet Gas - Submission in relation to current regulatory determination process for SAPN, AGN, Energex and Ergon - 24 July 2015

Authors
Multinet Gas
Content type
Document

QFM Production Pty Ltd - Submission to SA Power Networks Revised Regulatory Proposal - 10 July 2015

Authors
QFM Production Pty Ltd
Content type
Document

Renmark Irrigation Trust - Submission to AER’s Preliminary Decision and SA Power Networks revised Proposal 2015-2020 - 24 July 2015

Authors
Renmark Irrigation Trust
Content type
Document

Riverland Wine - Submission regarding SA Power Networks revised Regulatory Proposal (2015-2020) - 24 July 2015

Authors
Riverland Wine
Content type
Document

SACOSS - Submission to the Australian Energy Regulator on SA Power Networks’ Revised Regulatory Proposal 2015-20 - 24 July 2015

Authors
South Australian Council of Social Service (SACOSS)
Content type
Document

SAWIA - Submission in response to SA Power Networks’ Revised Regulatory Proposal 2015-20 - 24 July 2015

Authors
South Australia Wine Industry Association (SAWIA)
Content type
Document

TGP Almonds - Submission to SA Power Networks Revised Regulatory Proposal - 14 July 2015

Authors
TGP Almonds
Content type
Document

United Energy - Submission in relation to current regulatory determination process for SAPN, AGN, Energex and Ergon - 24 July 2015

Authors
United Energy Distribution
Content type
Document

UnitingCare - Submission in response to revised regulatory proposals for 2015-20, SA Power Networks, Electricity Distribution business and AER preliminary determination - 24 July 2015

Authors
UnitingCare Australia
Content type
Document

Wakefield Regional Council - SA Power Networks Regulatory Proposal - 24 July 2015

Authors
Wakefield Regional Council
Content type
Document

Yatco - Submission to SA Power Networks Regulatory Proposal (2015-2020) - 24 July 2015

Authors
Yatco
Content type
Document

Central Irrigation Trust - Submission on SA Power Networks revised regulatory proposal - 10 July 2015

Authors
Central Irrigation Trust
Content type
Document

Energy Consumers Coalition of SA - Submission on SA Power Networks' revised proposal - July 2015

Authors
Electricity Consumers Coalition of SA (ECCSA)
Content type
Document

District Council of Loxton Waikerie - Letter of support SA Power Networks - upgrade worst performing feeders - 29 July 2015

Authors
District Council of Loxton Waikerie
Content type
Document

Yorke Peninsula Council - letter of support for AER preliminary decision - 24 July 2015

Authors
Yorke Peninsula Council
Content type
Document

Knispel Bros Pty Ltd - Submission on SA Power Networks' revised proposal - 9 July 2015

Authors
Knispel Bros Pty Ltd
Content type
Document

Fran Newby - Submission on SA Power Networks' revised proposal - July 2015

Authors
Fran Newby
Content type
Document

Berri Resort Hotel - Submission on SA Power Networks revised proposal - 22 July 2015

Authors
Berri Resort Hotel
Content type
Document

Australian Olive Assoc - Submission on SA Power Networks' revised proposal - 13 July 2015

Authors
Australian Olive Association
Content type
Document

District Council of Karoonda East Murray - Submission on SA Power Networks' revised proposal - July 2015

Authors
District Council of Karoonda East Murray
Content type
Document

Dad's Olive Oil - Letter supporting CIT submission to SA Power Networks' revised proposal - 16 July 2015

Authors
Dad's Olive Oil
Content type
Document

Riverland Energy Association - Submission to SA Power Networks' regulatory proposal - 20 July 2015

Authors
Riverland Energy Association
Content type
Document

EUAA - Submission to AER preliminary decision and SA Power Networks' revised proposal - 24 July 2015

Authors
Energy Users Association of Australia (EUAA)
Content type
Document

Minister for Mineral Resources and Energy - Submission to SA Power Networks revised proposal - 4 August 2015

Authors
Minister for Mineral Resources and Energy - SA
Content type
Document

AGL - Letter to AER on SA Solar off peak hot water - July 2015

Authors
AGL
Content type
Document

Late submissions

The AER received late submissions which were not considered.

AER - Letter to SA Power Networks on rate of return and gamma materials - 28 October 2015

Authors
AER
Content type
Document

SA Power Networks - Letter to AER on rate of return and gamma materials - 23 October 2015

Authors
SA Power Networks
Content type
Document

SA Power Networks - Attachment A list of attachments to letter to AER of 23 October 2015 - October 2015

Authors
SA Power Networks
Content type
Document